Powering accountability: 10 RPP/PDU panels commissioned at a Slough data centre

An electrical engineer in a white hard hat and yellow Aphex hi-vis vest works at an open, glowing orange switchgear cabinet in a dark industrial switchroom.

Powering accountability: 10 RPP/PDU panels commissioned at a Slough data centre

In a data centre, power monitoring has to serve two different needs. Operations teams need to know when a critical breaker trips. Tenants need energy usage to be measured and allocated accurately.

Both depend on the same foundation: a properly connected, configured and verified monitoring system.

At a recent data centre project in Slough, Aphex Systems commissioned metering and monitoring across 10 remote power panel/power distribution unit (RPP/PDU) panels. The scope brought together dedicated CAT6A network infrastructure, breaker-status integration into the building management system (BMS), Janitza circuit-level metering and GridVis configuration for tenant billing and capacity alerts.

With 144 outgoing ways commissioned per PDU, the project covered 1,440 metered circuits. At that scale, attention to detail was essential—not only at the meter, but throughout the data path.

Building the network before bringing devices online

Reliable monitoring starts with reliable connectivity.

Aphex installed, tested and certified a dedicated CAT6A network linking the metering and monitoring devices. This established the communications backbone before the devices went live.

The network was a core part of the commissioning scope, rather than an afterthought. Meter readings and status information need a dependable route to the systems that use them. Testing that infrastructure first gave the team a verified foundation for the subsequent integration work.

Bringing critical breaker status into the BMS

Energy readings show how circuits are being used. Breaker status provides a different piece of operational information: whether a critical breaker has tripped.

Aphex integrated critical breaker status into the BMS so that trips generate alarms for the operations team.

Every monitoring point was tested end to end. This checked the complete path from the field status to the BMS indication and alarm, rather than stopping at the physical connection.

That distinction matters. A connected point is not necessarily a verified point. Operators need confidence that the status they see corresponds to the correct breaker and that the alarm reaches the system as intended.

Commissioning 1,440 circuits with Janitza metering

The circuit-level metering used Janitza UMG 800 equipment with 800-CT24 modules.

Across the 10 panels, Aphex commissioned 144 outgoing ways per PDU, delivering a total of 1,440 metered circuits.

Each current transformer (CT) was verified for mapping, phase and reading accuracy. These checks addressed three practical questions:

  • Is the reading associated with the correct circuit?
  • Is the phase assignment correct?
  • Does the reading accurately reflect the circuit being measured?

For tenant allocation and operational reporting, those details are fundamental. A reading needs to be more than visible on screen: it needs to be attributable to the right circuit.

By checking every CT, the commissioning team established the metering foundation for the reporting and billing configuration that followed.

Configuring GridVis for tenant billing and capacity alerts

Aphex configured GridVis to support tenant billing by circuit group, bringing individual circuit readings into the groupings needed for tenant allocation.

The team also configured over-usage alerts against contracted capacity. This gives operators visibility when usage exceeds the configured contractual threshold, supporting review and follow-up.

These alerts are a monitoring function, not a substitute for electrical protection or an automatic capacity limit.

Together, circuit grouping and capacity alerts make the metering data useful beyond individual readings. They help connect measured usage to tenant accountability and the management of available capacity.

Connecting operational visibility with accountable billing

The completed system gives the client visibility across the commissioned power distribution—from the communications network and critical breaker status to individual metered circuits.

Each element serves a distinct purpose:

  • CAT6A infrastructure provides the dedicated communications backbone.
  • BMS integration brings critical breaker status and trip alarms into the operational view.
  • Janitza metering provides circuit-level usage data.
  • GridVis configuration supports tenant billing by circuit group and alerts against contracted capacity.

Taken together, that information supports operational decisions, fair energy allocation and capacity planning.

The value lies in the complete chain. Network certification, end-to-end point testing and CT verification all contribute to confidence in the information the client uses.

Precision at every stage

Commissioning 10 panels and 1,440 circuits requires consistent checking across repeated tasks. The project depended on close coordination between the client, site teams and Aphex engineers, with precision at each stage of delivery.

Thank you to everyone involved in bringing the installation into service.

Planning circuit-level metering or BMS integration?

Whether the priority is breaker visibility, tenant energy allocation or monitoring against contracted capacity, the starting point is a clear understanding of the data required—and a commissioning process that verifies how it reaches the operational systems.

Aphex Systems supports Janitza metering, GridVis configuration and BMS integration for data-centre environments.